February 2023 Update
![Abatement Process at RFK Stadium]()
Smoot Construction Company of Washington, DC has completed the abatement of identified asbestos containing materials within RFK Stadium. Non-structural demolition of plumbing fixtures, equipment and upper-level seats, among other stadium components, will continue in February. Smoot has also been coordinating with local utility companies and District agencies to disconnect water, sanitary sewer and electrical infrastructure servicing the stadium.
Through the end of January 2023, nearly 368 tons of metal and 16 tons of plastic material were recycled and approximately 719 tons of non-structural construction debris was removed from the stadium.
Certified Business Enterprise (CBE) participation in the project is at 75%, with Small Business Enterprise participation at 54%.
Events DC is in the process of securing approvals for structural demolition.